Status

As of May 2026
Phase: Design

The design consultant, KPFF, submitted 100% design plans to the City on May 4, 2026. The City will have one month to review the plans and provide comments back to KPFF to address.  Once all the comments are addressed, the City will begin preparing the project for advertisement and accepting bid proposals. Construction is likely to begin in summer or fall of 2026. 

Project Overview

The 19th Avenue NE Sidewalk Project will construct sidewalk on the west side of 19th Avenue NE and sidewalk and curb ramp improvements at the major intersections between NE 196th Street and 244th Street SW (NE 205th Street).

Location of new sidewalk project on 19th Avenue NE extending from NE 196th Street north to NE 205th Street

Project location

This project is part of the 2018 voter-approved effort to build and repair sidewalks throughout Shoreline.

Project improvements include:

  • Pedestrian facilities with curbs and gutters
  • Curb ramps
  • Drainage improvements

Project Timeline

  • Preliminary Design: Summer/Fall/Winter 2024
  • Final Design: Mid 2025
  • Construction: Summer 2026

Tree Impacts

We are early in the design process but anticipate that this project may impact up to 10 trees based on an arborist assessment of the trees in the project area.

NOTE: The format of the arborist report does not meet current digital accessibility standards so we are unable to provide it on the City’s website. To receive a copy of the arborist report, please email Tavia Tan at ttan@shorelinewa.gov. 

Community Outreach

Online Open House - December 17, 2024 - January 24, 2025

Open House  - December 17, 2024

Additional information

May 20, 2024 City Council meeting staff report