As of September 2025
Phase: Design
The City submitted 90% design comments to KPFF on August 22, 2025. Construction has been pushed out to 2026, due to competing projects happening in 2025.
Project Design Open House
An online open house was held December 17, 2024 through January 24, 2025. View a draft report of the feedback we received.
An in-person open house was held on Tuesday, Dec. 17. View a report of the feedback we heard during the event.
Project Overview
The 19th Avenue NE Sidewalk Project will construct sidewalk on the west side of 19th Avenue NE and sidewalk and curb ramp improvements at the major intersections between NE 196th Street and 244th Street SW (NE 205th Street).
Project location
This project is part of the 2018 voter-approved effort to build and repair sidewalks throughout Shoreline.
Project improvements include:
- Pedestrian facilities with curbs and gutters
- Curb ramps
- Drainage improvements
Project Timeline
- Preliminary Design: Summer/Fall/Winter 2024
- Final Design: Mid 2025
- Construction: Summer 2026
Tree Impacts
We are early in the design process but anticipate that this project may impact up to 10 trees. An arborist assessment of the trees in the project area is available for review.