Status

As of April 2026
Phase 1: 90% Design
Future Phases: 60% Design

The City's design team achieved the 60% design milestone for the full corridor in August 2022. Design for the first phase of the project reached 90% design in September of 2025. Construction of Phase 1 is estimated to begin in late 2027.

Project location

The N 175th Street Corridor project area spans the length of N 175th Street between Stone Avenue N and I-5. 

The N 175th Street Corridor project area spans the length of N 175th Street between Stone Avenue N and I-5. 

Project Overview 

The 175th Street corridor is one of Shoreline's most active east-west arterials, connecting the city's busiest north-south roadways. In 2022, N 175th served the second highest volume of traffic in the city; only Aurora/Hwy 99 served more travelers. The corridor is a key transit route, connector to I-5 and the east side of the city, freight corridor, and backbone for emergency response. Four bus routes operate on the corridor with a busy park and ride lot located at the intersection of N 175th and Meridian. Hundreds of high school, elementary, and preschool students and their families use N 175th on a daily basis as they travel to Shorewood High School, Meridian Park Elementary School, and Edwin Pratt Early Learning Center. 

The N 175th Street Corridor project will improve safety and mobility for all corridor users, support growth, and provide better facilities for transit and bicyclists. Improvements include reconstruction of the existing street to provide two traffic lanes in each direction; medians and turn pockets; bicycle lanes; a shared-use path; curb, gutter, and sidewalk with planter strip where feasible; roadway illumination; pedestrian beacons at Ashworth and Wallingford Avenues; new signal system at the intersection of N 175th Street and Meridian Avenue; utility undergrounding; landscaping; and retaining walls.  

The project will be conducted in phases, with the first phase focused on the intersection of N 175th Street and Meridian and the Ronald Bog frontage.

Artist rendering of the completed corridor shows trees lining the street median and the amenity zones between the sidewalks and the roadway. Bicyclists ride in the bike lane.
Artist’s rendering of the completed corridor from the intersection of N 175th and Meridian Avenue N looking west. 

Seismic activity and Ronald Bog 

During our design work we discovered that a significant seismic event could cause soil failure near Ronald Bog. This could have significant impacts including a partial collapse of the roadway and underground utilities into the bog. We applied for and were awarded a FEMA Building Resilient Infrastructure and Communities (BRIC) grant for seismic mitigation/road work adjacent to the susceptible areas near Ronald Bog and including the 175th Street/Meridian Avenue intersection. 

175 corridor seismic hazard map showing peat and weak fill soils beneath N 175th Street. This area spreads from just west of the Meridian intersection east to just past Ronald Bog.

Geotechnical analysis identified that a large portion of N 175th Street and Meridian Avenue N are built upon a peat bog and weak fill soils (highlighted in red). 

Why improve the corridor? 

Current conditions 

In its current condition, the corridor is missing segments of sidewalk; particularly on the north side of the street. There is no buffer between the existing sidewalk and the roadway. Accessibility improvements are greatly needed as segments of existing sidewalks are blocked by trees or utility poles and are too narrow for people in wheelchairs or using strollers to get through. Missing and narrow sidewalks also limit the bus stop facilities on the route. 

Shoreline has few east-west connections for bicyclists to cross the City. The lack of dedicated bicycle facilities on N 175th and high traffic volumes have discouraged bicyclists from using the corridor.  

Traffic congestion is an ongoing problem during the busiest parts of the day. The intersections at N 175th and Meridian and N 175th and I-5 become heavily congested during the evening rush hours. In the future, traffic will continue to grow, which will increase the delay at all intersections on the corridor. 

Inaccessible sidewalks

Missing and narrow sidewalks

Climate goals 

Shoreline  - along with communities around the world – is already experiencing the impacts of a changing climate. As a City we have an ongoing commitment to address the climate crisis and work towards a more just, resilient, and thriving future for everyone in Shoreline. 

A primary goal in our 2022 Climate Action Plan is to reduce emissions 60% by 2030. The City’s 2019 greenhouse gas emissions inventory shows that transportation is Shoreline’s largest greenhouse gas emissions source, accounting for 55% of total community-wide emissions. Most of these emissions come from gasoline use in passenger vehicles.  

Reducing community-wide driving is one of our top strategies for reducing emissions. To do that, we are working to create dense, bikeable, and walkable communities concentrated around transit. We can’t create dense walkable communities without making significant improvements to our transportation infrastructure. This includes repairing our existing sidewalks, constructing new sidewalks, and improving transportation corridors to allow for better access for pedestrians, transit, and vehicle traffic. We cannot meet our goal of reducing vehicle emissions without providing viable alternatives to them.  

To make improvements like safer sidewalks that are accessible to all users, bicycle facilities, better transit access, and reduced traffic congestion we will need to widen the footprint of N 175th. 

Tree Impacts

We prepared an arborist report during the early design process for the entire corridor. The December 2022 draft arborist report provided an inventory of trees along the entire corridor. In this report, 274 trees were identified as requiring removal so that improvements could be successfully constructed. The arborist also recommended 191 opportunities where trees could be retained using tree protection measures. 

Currently the project is planned for construction in multiple phases. The first phase is centered on the intersection of N 175th Street and Meridian Avenue N. For this first phase, a separate Inventory and Assessment Summary Report was prepared in May of 2024, which reviewed trees in the planned area of improvements. In the phase 1 report, 37 trees were identified as requiring removal and 44 opportunities where trees could be retained using tree protection measures were identified. The number of replanted trees for Phase 1 will be set in 2026.

The format of these reports does not meet current digital accessibility standards so we are unable to provide them on this website. To receive a copy of the arborist reports, please email Tavia Tan at ttan@shorelinewa.gov.

Phase 1 Improvements 

The first phase of the N 175th Street Corridor Project is scheduled to begin construction in 2027. Phase 1 limits are defined by the seismic mitigation work area illustrated in the map below.

The phase 1 improvements are centered on the Meridian intersection and east to the limits of Ronald Bog. Additional work on the other three legs of the intersction.

Meridian Avenue N intersection and Ronald Bog frontage

Corridor improvements in Phase 1 will include 12-foot shared-use paths along both sides of the roadway. The shared use paths will be separated from the traffic lanes by planter strips on both sides of the road way. This segment of N 175th does not include an on-street bike lane.

Section 3: N175th Street east of Meridian Ave N. Two eastbound and two westbound lanes, one westbound turn lane. 5 foot planter strips on both sides separate traffic lanes from 12 foot shared uses paths.

Intersection of Meridian Avenue N and N 175th Street

The goal for the intersection at Meridian Avenue N and N 175th Street is to improve the intersection with a new traffic signal system with longer turn lanes and improved bike and pedestrian facilities while minimizing environmental impacts at Ronald Bog and maintaining connectivity to the recently constructed sidewalks at Meridian Park Elementary.

Improvements on Meridian Avenue N will connect to the Meridian Avenue N Safety Improvements project, which added bike facilities to Meridian between N 155th Street and N 175th Street in 2023. Additional information can be found on the Meridian Avenue N Safety Improvements project webpage.

Future phases

Future phases consist of all areas between Stone Avenue N and I-5 that are not included in Phase 1. The designs shown below are concepts of the work to come in these future phases. The timeline for construction is not yet determined and the segments in the design concepts below may be divided into different construction periods.

Design concepts between Stone Avenue N to Meridian Avenue N

The Council approved design concept provides a shared-use path in the westbound (uphill) direction and an on-street buffered bike lane, and a widened sidewalk in the eastbound direction (downhill) between Stone Avenue N to Meridian Avenue N. The uphill slope of the westbound direction limits the speed of people biking who wish to use the shared-use path, while those traveling eastbound (downhill) will have an on-street buffered bike lane which provides separation from both vehicles and people using the sidewalk. The design also includes a center median which allows for a new pedestrian crossing at Ashworth Avenue N and safety enhancements to the existing crossing at Wallingford Avenue N. 

Concept drawing for Stone Avenue N to Wallingford

Concept for Stone to Wallingford is four lanes of traffic separated by a 6 foot raised median planted with trees. On the north side, a 5.5 foot planter strip separates traffic lanes from a 13 foot shared use path. On the south there is an on-street bike line, a 3.5 foot landscape buffer, and a 10 foot sidewalk.

Cross section view between Densmore and Wallingford

Section 2 N 175th Street between Densmore and Wallingford Dimensions. Illustrates grade of existing retaining walls and how much will need to be removed to expand to fit a pedestrian and bicycle facilities.

Concept drawing of Wallingford to Meridian

Preferred concept Wallingford to Meridian shows four travel lanes separated by a tree-planted raised median. 13 foot shared use paths on both sides of the street are separated from the road by planter strips. There is an on-street bike lane on the eastbound side of the street.

East limits of Phase 1 to I-5

This segment of the project will require close consultation with the Washington State Department of Transportation (WSDOT) when developing the final design. 

Concept drawing of east limits of Phase 1 to I-5

Concept drawing of east limits of Phase 1 to I-5. Two eastbound and two westbound lanes, one westbound turn lane. 5 foot planter strips on both sides separate traffic lanes from shared uses paths.

Background

Council Approved Design Concept

On February 1, 2021, City Council approved the preferred design concept for the 175th Corridor Improvements Project. Using feedback received from over 1,500 participants through public outreach during the past two years, we were able to establish the community’s top three priorities for the corridor – (1) pedestrian walkability, (2) flow of traffic, and (3) transportation safety. The community provided feedback on how the initial design concepts met these priorities, and we combined this feedback with technical analysis to develop the preferred design concept. 

Public Outreach

Phase three outreach was completed in fall 2021. We gathered your input on public art, urban design, and landscape features for the N 175th Street Corridor Improvements Project.

Public input indicates preference toward the use of natural materials and support for retention of street trees in the landscaping design. Indigenous art and nature-inspired art are preferred with possible art installations sited at bus stops and sidewalks. The community also preferred keeping the pony statues at the 175th Street gateway sign.

Check back here for project updates and information or sign up for email alerts using the eNotification Signup section in the right-hand column of this page to stay up to date.  

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Windows Media Player Download Word Viewer Download Excel Viewer Download PowerPoint Viewer

Translations 

English  If you would like to communicate with the City of Shoreline or review a document in another language, please send your request along with your contact information to clk@shorelinewa.gov or call 206-801-2700.

Spanish   Si quisiera comunicarse con la ciudad de Shoreline o revisar un documento en otro idioma, envíe su solicitud junto con su información de contacto a clk@shorelinewa.gov o llame al 206-801-2700.

Chinese (Traditional)  如果您想與 City of Shoreline 進行交流或檢視以另一種語言提供的文件,請將您的請求連同您的聯絡資訊發送到 clk@shorelinewa.gov 或請致電 206-801-2700。

Chinese (Simplified)  如果您想与 City of Shoreline 进行交流或查看以另一种语言提供的文档,请将您的请求连同您的联系信息发送到 clk@shorelinewa.gov 或请致电 206-801-2700。

Korean  City of Shoreline에 연락하고 싶거나 다른 언어로 된 문서를 검토하려면 연락처 정보와 함께 요청서를 clk@shorelinewa.gov로 제출하거나 206-801-2700번으로 전화해 주십시오.

Vietnamese  Nếu quý vị muốn liên hệ với Thành phố Shoreline hoặc đọc tài liệu bằng ngôn ngữ khác, vui lòng gửi yêu cầu cùng với thông tin liên hệ tới địa chỉ clk@shorelinewa.gov hoặc gọi 206-801-2700.

Tagalog  Kung gusto mong makipag-usap sa Lungsod ng Shoreline o suriin ang isang dokumento sa ibang wika, pakipadala ang iyong kahilingan kasama ng iyong impormasyon sa pakikipag-ugnayan sa clk@shorelinewa.gov o tumawag sa 206-801-2700.

Amharic  የሾርላይን ከተማ ጋር ለመገናኘት ከፈለጉ ወይም አንድን ሰነድ በሌላ ቋንቋ ለመከለስ ከፈለጉ ጥያቄዎን ከመገኛ መረጃዎ ጋር በማድረግ በ clk@shorelinewa.gov ላይ ኢሜይል ያድርጉ ወይም በ 206-801-2700 ላይ ስልክ ይደውሉ።

Tigrigna  ምስ ከተማ ሾርላይን ክትዘራረቡ ወይ ድማ ሰነዳትኩም ብካልእ ቋንቋ ከተገምግሙ ምስ እትደልዩ፡ ጠለባትኩም ምስናይ ናይ መርከቢ ሓበሬታኹም ናብ clk@shorelinewa.gov ስደዱ ወይ ድማ ብቑጽሪ 206-801-2700 ደዉሉ።

Russian  Если вы хотите связаться с представителями города Шорлайн (Shoreline) или ознакомиться с документом на другом языке, отправьте запрос вместе со своими контактными данными на адрес clk@shorelinewa.gov или позвоните по телефону 206-801-2700.

Japanese  City of Shoreline とのご連絡、または他の言語での資料閲覧をお望みでしたら、お客様のご連絡先を添えたリクエストをclk@shorelinewa.gov まで送信いただくか、 206-801-2700 までお電話をお願いいたします。

Khmer (Cambodian)  ប្រសិនបើលោកអ្នកចង់ប្រាស្រ័យទាក់ទងជាមួយទីក្រុង Shoreline ឬពិនិត្យឯកសារឡើងវិញជាភាសាផ្សេងទៀត សូមផ្ញើសំណើរបស់អ្នកជាមួយព័ត៌មានទាក់ទងរបស់អ្នកទៅ clk@shorelinewa.gov ឬហៅទូរស័ព្ទទៅលេខ 206-801-2700។