Status

As of September 2026
Phase 1: Construction - east of Interstate 5 (I-5)
Phase 2: Construction- west of I-5

Phase 1 of the 148th Street Non-Motorized Bridge is under construction! Massana Construction began work on the side of the freeway in December 2023. Construction on this portion of the project is expected to be complete in mid 2026.

Phase 2, west of I-5, began construction in June 2025. Kraemer North America is performing the work for this phase. The bridge structure is being assembled on the west side of I-5 near the 145th Street southbound off-ramp. We anticipate the bridge span will be placed on the bridge piers overnight in early November 2026.

Completion of the project and bridge opening is expected in spring 2027.

Upcoming overnight full closure of I-5

In fall 2026 we will lift the bridge span into place across the freeway. To do this safely, we’ll need to completely close I-5 in both directions for one night between the N 145th Street exit and the N 175th Street exit. 

Lane reductions will begin at 9:00 p.m. on a Saturday night in late October or early November. The freeway will be fully closed between midnight and 5:00 a.m. on Sunday. Once the bridge is in place, WSDOT will reopen I-5 one lane at a time. I-5 should be fully reopened by 6:00 a.m. on Sunday.

Date:

  • Early November 2026

Closure location:

  • All lanes of I-5 in both directions between the N 145th Street and N 175th Street exit

Detours:

  • Southbound: Exit at N 175th Street, west to Aurora Avenue N or east to 15th Avenue NE, south to N 145th Street
  • Northbound: Exit at N 145th Street, west to Aurora Avenue N or east to 15th Avenue NE, north to N 175th Street

I-5 closed between NE 145th Street and NE 175th Street. Detours are Aurora Avenue N and 15th Avenue NE

  • People traveling through the region can avoid the closure by detouring to I-405 in Lynnwood or Tukwila

Avoid the closure area completely by taking I-405 instead of I-5 when traveling through the region

Project Overview

The City of Shoreline is growing and changing. New development has brought more residents to Shoreline. All residents need new ways to safely connect to light rail and future bus rapid transit options at the Shoreline South/148th Station. To meet these needs, the City of Shoreline is building a new pedestrian and bike bridge crossing over I-5 at N 148th Street.

The bridge will provide a vital new pedestrian/bike connection over I-5 for people walking, biking, and rolling. The bridge will improve safety, reduce travel times, and improve access to regional light rail and bus transit at the Shoreline South/148th Station.

Tree Impacts

Four trees were removed in Phase 1, as many trees had already been removed in this area for the Sound Transit Lynnwood Link Extension Project. This phase of the project does not include trees being planted.

Phase 2 of the project includes construction of the bridge and the connection to 1st Avenue NE. This project removed 47 significant trees and another 16 trees that are not considered significant (total of 63 trees). Most of the trees identified for removal were necessary to build the bridge and put it in place. We designed the project to protect 9 trees located on the Unitarian Church property near the connection to 1st Avenue NE.

Following the bridge project, WSDOT will be constructing a project to daylight Thornton Creek within the WSDOT right-of-way. Based on the timing of the projects, WSDOT has asked that the City not replant trees that are within the footprint of their daylighting project. The Thornton Creek project will have an extensive restoration plan that will include tree replanting. The 148th Bridge Project is planting 7 trees on private property outside the footprint of the WSDOT project.

NOTE: The format of the arborist report does not meet current digital accessibility standards so we are unable to provide it on the City’s website. To receive a copy of the arborist report, please email Tavia Tan at ttan@shorelinewa.gov. 

Location and Design

The new bridge will stretch across I-5 at N 148th Street, be wide enough to accommodate pedestrians and bicyclists, and comply with Americans with Disabilities Act (ADA) standards.
148th Street Non Motorized Bridge Project Map Area

The project team sought public input throughout the early design and planning phases through community briefings, an online public meeting, and online open house. Community input contributed to decisions about what type of bridge will be built, and how the bridge will connect to the new station on the east side of I-5 and to 1st Avenue NE on the west side of I-5. The project consists of these three elements, which are shown below:

West Trail Connection
Bridge span over I-5
East Bridge Landing

Public Outreach to Date

Information from our earlier public outreach efforts is included below:

  • June 2023: Construction postcard mailed to nearby residents. 
  • October 2021: Virtual open house
  • November 2021: Online presentation
  • April 2020: Virtual open house
  • April 23, 2020: Webinar presentation

Background

In 2016 and 2017, the City of Shoreline did a study to evaluate and recommend options for linking the communities on the west side of I-5 to the future Sound Transit Shoreline South/145th Station. City of Shoreline staff, Shoreline City Council, and consulting engineers evaluated five options. Public comment was provided at Shoreline City Council meetings.

The City estimated the location at N 148th Street would cost the least to construct, likely draw the most users, and of the routes possible, provide the shortest and most direct access to the Shoreline South/145th Station. The City also reviewed WSDOT and Sound Transit regulations in order to address safety needs around and across I-5. Shoreline City Council approved this location in February 2017.

The project team considered several options for each portion of the project. The team presented three design options for the bridge span, three design options for the East Bridge Landing, and two for the West Trail Connection. On June 1, 2020, City Council approved the following options as the combined preferred alternative that will move forward through design and construction. These options were selected based on public input and technical needs.

  • West Trail Connection: Full Build-Out (North)
  • Bridge Span over I-5: Tied Arch Bridge
  • East Bridge Landing: Direct Ramp

Translations 

English: If you would like to communicate with the City of Shoreline or review a document in another language, please send your request along with your contact information to clk@shorelinewa.gov or call 206-801-2700. Translated materials are provided free of charge.

Amharic: ከCity of Shoreline ጋር ለመገናኘት ከፈለጉ ወይም አንድን ሰነድ በሌላ ቋንቋ ለማየት ከፈለጉ፣ ጥያቄዎን ከዕውቅያ መረጃዎ ጋር በማድረግ ወደ clk@shorelinewa.gov ኢሜይል ይላኩ ወይም ወደ 206-801-2700 ይደውሉ። የተተረጎሙት መረጃዎች ያለክፍያ ይቀርባሉ።

Arabic: إذا كنت ترغب في التواصل مع City of Shoreline أو ترغب بمراجعة مستند بلغة أخرى، يُرجى إرسال طلبك مصحوبًا بمعلومات التواصل معك عبر clk@shorelinewa.gov أو اتصل بنا على 206-801-2700. تقدم المواد المترجمة مجانًا.

Chinese (Simplified): 如果您想与 City of Shoreline 进行交流或查看其他语言版本的文档,请将您的请求连同您的联系信息发送到 clk@shorelinewa.gov 或致电 206-801-2700。翻译材料免费为您提供。

Chinese (Traditional): 如果您想與 City of Shoreline 進行交流或檢視以另一種語言提供的文件,請將您的請求連同您的聯絡資訊發送到 clk@shorelinewa.gov 或請致電 206-801-2700。翻譯資料免費為您提供。

Japanese: City of Shorelineとのやり取りや、文書を別の言語でご覧になることをご希望の場合は、ご希望内容と連絡先情報を clk@shorelinewa.gov までメールでお送りいただくか、 206-801-2700 までお電話ください。翻訳資料は無料で提供しています。

Khmer: ប្រសិនបើអ្នកចង់ទំនាក់ទំនងជាមួយ City of Shoreline ឬពិនិត្យឯកសារជាភាសាផ្សេងទៀត សូមផ្ញើសំណើរបស់អ្នករួមជាមួយនឹងព័ត៌មានទំនាក់ទំនងរបស់អ្នកទៅកាន់ clk@shorelinewa.gov ឬទូរស័ព្ទទៅ 206-801-2700 ។ សម្ភារៈបកប្រែត្រូវបានផ្តល់ជូនដោយឥតគិតថ្លៃ។

Korean: City of Shoreline에 연락하고 싶거나 다른 언어로 된 문서를 검토하려면 연락처 정보와 함께 요청서를 clk@shorelinewa.gov 로 제출하거나 206-801-2700 번으로 전화해 주십시오. 번역본은 무료로 제공됩니다.

Russian: Если вы хотите связаться с представителями City of Shoreline или ознакомиться с документом на другом языке, отправьте запрос вместе со своими контактными данными на адрес clk@shorelinewa.gov или позвоните по номеру 206-801-2700. Переведенные материалы предоставляются бесплатно.

Spanish: Si desea comunicarse con la City of Shoreline o consultar un documento en otro idioma, envíe su solicitud junto con su información de contacto a clk@shorelinewa.gov o llame al 206-801-2700. El material traducido se entrega sin cargo.

Tagalog: Kung nais ninyong makipag-ugnayan sa City of Shoreline o sumuri ng dokumento sa ibang wika, mangyaring ipadala ang inyong kahilingan kasama ang inyong impormasyon sa pakikipag-ugnayan sa clk@shorelinewa.gov o tumawag sa 206-801-2700. Ang mga isinaling kagamitan ay ipinagkakaloob nang walang bayad.

Tigrinya: ምስ City of Shoreline ክትዘራረቡ ወይ ድማ ሰነዳትኩም ብካልእ ቋንቋ ክትሪኡ ምስ እትደልዩ፣ ጠለባትኩም ምስ መራኸቢ ሓበሬታኹም ናብ clk@shorelinewa.gov ለኣኹ ወይ ድማ ብቑፅሪ ስልኪ 206-801-2700 ደዉሉ። ዝተተርጎመ ሓበሬታ ብነጻ ይቐርብ።

Vietnamese: Nếu bạn muốn liên hệ với City of Shoreline hoặc xem tài liệu bằng ngôn ngữ khác, vui lòng gửi yêu cầu cùng với thông tin liên hệ của bạn đến clk@shorelinewa.gov hoặc gọi 206-801-2700. Các tài liệu dịch thuật được cung cấp miễn phí.