Residential Addition

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

This checklist covers submittal requirements for a building permit for home additions and work that will impact the exterior of the home or increase square footage. Examples include: 

  • Additions to a residential home like adding a new bedroom or living space.
  • New or replacement decks, porches, patio coverings and awnings.
  • Conversion of existing unfinished – basement, attic, or garage – space to finished space.
  • New uninhabited detached spaces, such as detached garages and larger sheds.

This permit can also include: 

  • Partial demolition work, if required
  • Mechanical 
  • Plumbing  

All plumbing and mechanical work will be combined with building permit application and cannot be deferred. Electrical permits are through Washington State Labor & Industries (L&I), not through the City of Shoreline. 

How to Apply

Apply for this permit online at the City of Shoreline's eTRAKiT permitting portal. Once you are logged into your account, select Apply/New Permit from the left-hand sidebar and select the following permit type from the drop-down menu: Pre-Intake Record.

Once PIN requests are submitted, the rest of the intake process is facilitated by a permit technician. A permit technician will send further instructions by email to complete the process. 

Required Documents

Additional Documents (Possibly Required)

  • Arborist Report
    • If work is proposed within the critical root zone of any trees to remain on the site, then that work must be evaluated by an ISA certified arborist. The arborist must assess the potential impacts of development on the long-term health of trees to be retained. Negative impacts to these trees are not permitted.
    • Any specific tree protection measures recommended by the arborist must be shown and described on your plans.
  • Critical Areas Report(s)
    • Required for projects in or near environmentally critical areas, such as steep slopes, streams and wetlands.
  • Declaration of Covenant – Stormwater Facilities
    • Required for any project that proposes on-site stormwater facilities. Refer to Chapter 4.9 of the City’s Engineering Development Manual. The draft form does not need to be notarized or signed.
  • Geotechnical or Soils Report
    • Required for projects with fill or excavation of 500 cubic yards or more, when sites contain or are adjacent to slopes that are 15% or steeper, or when using certain storm drainage designs.
    • A geotechnical report or soils evaluation could be a required component of a critical areas report for certain types of environmentally critical areas. 
  • Heating System Sizing Form
    • Required for new residential construction and additions where the total new area exceeds 750 square feet, measured cumulatively.
  • Surface Water Report
    • Required for projects proposing 2,000 square feet or more of new and replaced hard surfaces. The report must follow the guidelines in Appendix C of the City’s Engineering Development Manual
  • Waste Diversion Plan and Salvage Assessment
    • Required for construction or alterations that exceed 1,000 square feet of gross floor area, or when demolition work is proposed. If required, the applicant must also provide a Waste Diversion Report prior to their final building inspection.
    • May be deferred to later rounds of review but must be submitted prior to permit issuance. 
  • Water Availability Certificate
    • Required for new residential construction and additions where the total new area exceeds 500 square feet, measured cumulatively.
    • Required for new residential construction and additions where both: (a) new (not replacement) plumbing fixtures are proposed, and (b) the property is served by the North City Water District. 

Additional Permits (Possibly Required)

These are additonal permits that may be required to accompany your buidling permit depending on your scope of work.