Status

As of June 2019
Phase: Construction

Next Steps

  • Construction is tentatively scheduled to begin the third week of June 2019
  • Construction Notification (Please note: the start of construction has been revised to occur the third week of June).

Schedule

  • Design Complete: Fall of 2018
  • Construction: June - November 2019 (tentative)

Overview 

Improvements are coming to the intersection of Meridian Avenue N and N 155th Street. This project will replace the current traffic signal with a new signal, which will improve traffic safety through the intersection. Curb, ramps and sidewalk will be replaced, and the new improvements will comply with the Americans with Disabilities Act (ADA). The signal and sidewalk improvements will increase pedestrian safety at the intersection. The finished project will also include mill and overlay with new asphalt and new pavement markings.Meridian_N155thStreet_Plan
Meridian Ave N & N 155th Street Plan Overview

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer