Home Search MenuStatus
As of December 2019
Phase: Construction
Next Steps
The new signal poles have arrived and construction has resumed. Over the final weeks of construction, installation of the new traffic signal, pavement markings and sidewalk will occur.
Schedule
- Design Complete: Fall of 2018
- Construction: June - December 2019
Overview
Improvements are coming to the intersection of Meridian Avenue N and N 155th Street. This project will replace the current traffic signal with a new signal, which will improve traffic safety through the intersection. Curb, ramps and sidewalk will be replaced, and the new improvements will comply with the Americans with Disabilities Act (ADA). The signal and sidewalk improvements will increase pedestrian safety at the intersection. The finished project will also include mill and overlay with new asphalt and new pavement markings.