As of April 2020
Phase: Construction

  • Construction Notification postcards were mailed to residents/property owners on March 7, 2020.
  • Construction activities are scheduled to begin on site the third week of April.

15thAveNE_155th-160th_WebsiteMap
Click on the map to view a larger image

On June 10, 2019, City Council approved a contract with Reid Middleton to begin design of the project. Design was completed in December 2019 and the construction contract was awarded in March 2020. Construction is scheduled to begin in the third week of April and is expected to go into the fall of 2020. Due to federal funding limits and time constraints, improvements to the west sidewalk will be deferred to a separate project and is scheduled for completion in mid to late 2020.

Overview and History

As part of the City's pavement preservation program, this project will provide pavement rehabilitation along 15th Avenue NE between NE 155th Street and NE 160th Street. The existing asphalt roadway will be milled down and resurfaced with asphalt overlay. In addition to work in the roadway, sidewalk repairs, curb ramp upgrades, and pedestrian push buttons modifications will be completed to meet the Americans with Disabilities Act (ADA) requirements. The area east of the curb line will not be impacted.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer